Kendall power station ‘sudden’ outage forces Eskom to increase blackouts
Eskom has announced escalating blackouts, with phase 4 due to begin at 10am on Tuesday morning.
Image: © Aekkarak Thongjiew/123rf.com
CAPE TOWN – Eskom has announced that it will be escalating the blackout, with Phase 4 due to start at 10am on Tuesday morning.
The Energy Authority said the sudden outage of three units at Kendal Power Station had forced them to increase their blackout levels.
READ: How to check load shedding schedule
This phase of the power outage will last until 5 a.m. Thursday.
The energy company said it would publish more detailed information in due course.
The sudden outage of three units at Kendall Power Station (1920MW peak generating capacity) has forced phase 4 load shedding from 10:00 THIS morning until 05:00 Thursday morning. A full statement will be published shortly